Central Station Lift Replacement

Central Station Lift Replacement


During nine weeks of construction, including over 20-night shifts, 2,570 hours were worked to complete the lift replacement which connects platforms 24 and 25 to the concourse. All works were completed within the original nine week programme, including additional works, which were incorporated with no delay to the project.

The project scope included dismantling and removing the existing lift and installing a new lift, with modification works to the existing lift shaft to comply and accommodate the replacement. Further works included the supply and installation of the mechanical ventilation system for the upgraded lift shaft and the upgrade of associated electricals including CCTV. The lift was also future proofed to allow for the planned floor level rise by Sydney Metro.

The works were undertaken within an underground environment, protected by smoke detectors and sprinklers which required special precautions to avoid any disruption to Central Station. Central Station is one of the busiest railway stations in Sydney and removals and deliveries took place at night to minimise the disruption to everyday commuters.

Sector

Rail

Value

$640k

Client

Sydney Trains

Duration

May 2019 - July 2019

  • Central Station Lift Replacement
  • Central Station Lift Replacement

Related Projects


Accreditations


Supply Nation Member
HIA
Master Builders Association NSW member

Gartner Rose would like to acknowledge the traditional custodians of this land. We pay our respects to Elders past, present and emerging.
We recognise their culture, traditions and connections to the land.

© 2024 Gartner Rose Pty Ltd. All rights reserved.