PROJECT COMPLETION - Kogarah Station Lift Replacements

Main Image
During sixteen weeks of construction, including multiple possessions, 4528 hours were worked to complete the replacement of two lifts at Kogarah Station.  

The project scope included the dismantle and removal of two existing lifts followed by the installation of two new fifteen passenger lifts. Modification works to the existing lift shafts were undertaken to comply with new standards and accommodate the replacement lift cars including waterproofing, structural alterations and painting of surrounding surfaces. Internal and external cladding works, further to new louvres were also undertaken to the lift shafts. 

Associated services were upgraded with new mechanical installations, a full electrical install including lighting and CCTV in addition to wet and dry fire upgrades involving new smoke detectors and sprinklers.  

All works were completed four days ahead of programme and complement our recent lift replacement projects at Wyong, Strathfield and Central Stations - all for Sydney Trains.

Congratulations to everyone for bringing this project to a safe completion and a special thank you to the project team, subcontractors and suppliers.  

CONTACT US
Head Office Level 16, 213 Miller Street North Sydney NSW 2060
Tel: 9935 5900
Contact Us
Health & Safety AS/NZS 4801 Certified System Enviroment ISO 14001 Certified System Quality ISO 9001 OHSAS 18001 Certified System Federal Safety Accreditation Master Building Association NSW Member Housing Industry Australia
Transport for NSW - Authorised Engineering Organisation