SUCCESSFUL POSSESSION - Point Clare Station 11th, 12th & 13th June (WE50)

Main Image

Over the possession weekend, a total of 2,164 hours to complete 100% of the work required, and the station was ready for commuters by Tuesday morning.

During WE50 the Point Clare team undertook the lift 1 and subway entry works that required temporary support of the existing embankment, tracks, and platform, to facilitate the demolition of the existing retaining walls and ramp. This allowed the placement of the blinding slab to enable the construction of the new entry in the week post WE50. The team also upgraded the existing stormwater infrastructure on the east of the station and undertook platform regrading works to remove non-compliant grades.

CONTACT US
Head Office Level 3, 15 Blue Street North Sydney NSW 2060
Tel: 9935 5900
Contact Us
Health & Safety AS/NZS 4801 Certified System Enviroment ISO 14001 Certified System Federal Safety Accreditation Master Building Association NSW Member Housing Industry Australia
Transport for NSW - Authorised Engineering Organisation