SUCCESSFUL POSSESSION - Point Clare Station 13th & 14th March (WE46)

Main Image

Over the possession weekend, 73 persons worked a total of 868 hours to complete 100% of the work required, and the station was ready for commuters by Monday morning.

As part of the Possession WE46 at Point Clare Station, Gartner Rose completed the undergrounding of 11KV Aerial Feeder.

Further work achieved over the possession weekend included:

  • installed 2 new UGOH poles,
  • terminated aerial cabling,
  • removed redundant power pole,
  • installed new inground cable route (approx. 50m),
  • tested, commissioned, and energised 11kV Feeder,
  • removed modular shoring box.


The possession was finished with zero FAI's, MTI's or incidents.  

Congratulations and thank you to the Gartner Rose staff, Transport for NSW project team, our subcontractors and suppliers for the effective utilisation of Possession WE46 at Point Clare Station.

CONTACT US
Head Office Level 3, 15 Blue Street North Sydney NSW 2060
Tel: 9935 5900
Contact Us
Health & Safety AS/NZS 4801 Certified System Enviroment ISO 14001 Certified System Federal Safety Accreditation Master Building Association NSW Member Housing Industry Australia
Transport for NSW - Authorised Engineering Organisation