SUCCESSFUL POSSESSION WE18 - Beecroft Station
Over the possession weekend, 123 persons worked 1192.5 total hours to complete 100% of the work required. The station was ready for commuters by Monday morning.
Gartner Rose undertook the regrade and resurfacing of the platform at the city end. It involved the installation of all platform furniture. Including 856m2 of platform regraded area, approximately 167m3 asphalt and sub-base removed. Five excavators (1.7t, 2 x 2.5t, 3.5t & 14t), two Hi-Rail Hydrema's, one Hi-Rail EWP, Hi-Rail Hi-AB and Hi-Rail Tilt Tray. The installation of three louvres to Lantern Building, cut-over of comms and CCTV to permanent SSER Room.
Congratulations and, thank you to the Gartner Rose staff, Transport for NSW project team, our subcontractors and suppliers for the effective utilisation of Possession WE18 at Beecroft Station.