SUCCESSFUL POSSESSION WE37 - Niagara Park Station

Main Image

We are delighted to advise the safe and successful utilisation of the scheduled Sydney Trains track possession over the weekend of the 13th and 14th March at Niagara Park Station

Over the possession weekend, 135 persons worked a total of 1,342 hours to complete 100% of the work required and the station was ready for commuters by Monday morning.

During this possession, Gartner Rose undertook the precast lift shaft installation of Lifts Two and Three, followed by the installation of their structural steel roof sheeting and canopies. 

Whilst the lift shafts were being installed, precast piling was undertaken at the Lift One location utilising a 60t percussive piling rig to drive 8 piles. A total of 102lm (36t) of precast pile was installed.

IMSB / Transformer installation was also undertaken, new cables were pulled into position ready for commissioning after the possession.

Pedestrians were able to safely utilise the pedestrian bridge while it remained open throughout the work due to traffic control management and monitoring of nearby danger zones.

All work undertaken was completed without any incidents.  


CONTACT US
Head Office Level 3, 15 Blue Street North Sydney NSW 2060
Tel: 9935 5900
Contact Us
Health & Safety AS/NZS 4801 Certified System Enviroment ISO 14001 Certified System Federal Safety Accreditation Master Building Association NSW Member Housing Industry Australia
Transport for NSW - Authorised Engineering Organisation