SUCCESSFUL POSSESSION WE50 - Niagara Park Station

Main Image

We are pleased to announce the safe and successful utilisation of the WE50 track possession over the long weekend of the 12th, 13th and 14th of June at Niagara Park Station.

Over the possession weekend, 114 persons worked a total of 943hours to complete 100% of the work required and the station was ready for commuters by Tuesday morning. The possession was finished with zero FAI's, MTI's, LTI's or incidents. 

As part of the Possession WE50 at Niagara Park Station, Gartner Rose undertook:

  • Install platform lift shaft lower canopy and upper screens.
  • Install lift 3 screens.
  • Regrade/ Resurface both car parks and platform. 175T of asphalt in total.
  • Commission new station power supply upgrade and station service mains switchboard.
  • Caulking of lift shafts.
  • Hoarding removal / furniture reinstatement.


Congratulations and thank you to the Gartner Rose staff, Transport for NSW project team, our subcontractors and suppliers for the effective utilisation of Possession WE50 at Niagara Park Station.

CONTACT US
Head Office Level 3, 15 Blue Street North Sydney NSW 2060
Tel: 9935 5900
Contact Us
Health & Safety AS/NZS 4801 Certified System Enviroment ISO 14001 Certified System Federal Safety Accreditation Master Building Association NSW Member Housing Industry Australia
Transport for NSW - Authorised Engineering Organisation