SUCCESSFUL POSSESSION - Waitara Station 11th, 12th and 13th June (WE50)

Main Image

Over the possession weekend, 148 people worked a total of 2645 hours to complete 100% of the work required, and the station was ready for commuters by Tuesday morning. As part of the Possession WE50 at Waitara Station, Gartner Rose had 15 pieces of plantworking on site.

Work achieved over the possession weekend included:

  • 8m of track removed and reinstalled on the up,
  • 15m of track removed and reinstalled on the down,
  • 57 piles installed,
  • 130 linear metres of hoarding installed on the platform (600mm diameter, various lengths)
  • Electrical diversion completed,
  • 2x temporary platform bridges installed,
  • 4 track welds completed, 4 fishplates joints completed,
  • 3x temporary ULX's installed.

The possession was finished with zero FAI's, MTI's or incidents.  

Congratulations and thank you to the Gartner Rose staff, Transport for NSW project team, our subcontractors and suppliers for the effective utilisation of Possession WE50 at Waitara Station.

CONTACT US
Head Office Level 3, 15 Blue Street North Sydney NSW 2060
Tel: 9935 5900
Contact Us
Health & Safety AS/NZS 4801 Certified System Enviroment ISO 14001 Certified System Federal Safety Accreditation Master Building Association NSW Member Housing Industry Australia
Transport for NSW - Authorised Engineering Organisation