Gartner Rose is delighted to announce the successful completion of Stage 4
of the Eveleigh Yards Project.
Zero lost time injuries on the project, in a difficult live working environment. Workers were faced with live 1500V traction cables and moving trains in close proximity at all times.
No interruptions were caused to this critical infrastructure site, a working maintenance depot.
Scope of works included:
- Construction of a new Train Decanting facility
- Construction of 420 metres of new maintenance facility upper level platforms
- Upgrade of Shore Power IMSB and Construction of new Shore facilities within maintenance depot.
- Demolition and Construction of New LV switch room an installation of new LV IMSB
- Construction of new HV compound and installation of 2 new 800Kva Pad Mounts
- Construction of new Earth Grid for HV upgrade.
Zero lost time injuries on the project, in a difficult live working environment. Workers were faced with live 1500V traction cables and moving trains in close proximity at all times.
No interruptions were caused to this critical infrastructure site, a working maintenance depot.
Scope of works included:
- Construction of a new Train Decanting facility
- Construction of 420 metres of new maintenance facility upper level platforms
- Upgrade of Shore Power IMSB and Construction of new Shore facilities within maintenance depot.
- Demolition and Construction of New LV switch room an installation of new LV IMSB
- Construction of new HV compound and installation of 2 new 800Kva Pad Mounts
- Construction of new Earth Grid for HV upgrade.