Pyrmont Pedestrian Crossing

Main Image


The works at Pyrmont Crossing were safely and successfully completed over a possession weekend for Transdev.

A total of 190 hours were worked to deliver the new pedestrian crossing at the Pyrmont Light Rail Station.

The project saw the removal of 12 timber crossing panels and replaced with new concrete precast panels. The scope was finished with painted pedestrian crossing markings and ready forpublic use by Monday morning. 