Strathfield Station Lift Replacements

Main Image
Over 12 weeks of construction, 8,200 hours were worked to complete the lift replacements, in time for the annual Royal Easter Show in Sydney.

The project saw the dismantle and removal of the existing lifts, installation of the new lifts with modification works to the existing lift shafts to comply and accommodate the replacements. Further works included the s upply and installation of the mechanical ventilation system for the upgraded lift shafts, the upgrade of associated electricals, and the replacement of a glass panel and the stainless-steel lift doors. 

While Strathfield Station is one of the busiest railway stations in Sydney, all deliveries took place at night with careful planning to minimise the disruption to everyday commuters.

Both lifts were open to the public in mid-April, where officials and the client attended to celebrate the project completion.

The project compliments our other recent contract award for the lift replacement at Central Station.


CONTACT US
Head Office Level 16, 213 Miller Street North Sydney NSW 2060
Tel: 9935 5900
Contact Us
Health & Safety AS/NZS 4801 Certified System Enviroment ISO 14001 Certified System Quality ISO 9001 OHSAS 18001 Certified System Federal Safety Accreditation Master Building Association NSW Member Housing Industry Australia
Transport for NSW - Authorised Engineering Organisation