Waterfall Station
Gartner Rose is delighted to announce the safe and successful completion of
Waterfall Station Easy Access Upgrade Project for TfNSW.
This project was finished 4 months ahead of practical completion.
Scope of works for this design and construct project included:
- New station entry with level access at overbridge level
- New lift from station entry to platform level
- Platform extension to form lift waiting area at platform level
- New canopies to station entry and platform
- New accessible toilets (replacing existing in platform building)
- Platform upgrading to achieve level access
- External works including modifications to footpaths
- Additional Lighting
- Additional CCTV coverage, containment and cabling
- Installation of the W19 Co-acting signal
- Way finding signage
- Temporary works
- Interchange works for kiss and ride, cycle shelter and storage facilities.
- Hearing Induction Loop in critical areas.
- Station Passenger Information (SPI)
Click here to read about the challenges and innovations faced in
this project.