Gartner Rose Gosford Hospital Redevelopment

Gosford Hospital Project Completion


Gartner Rose is delighted to announce the safe and successful completion of the roofing works at Gosford Hospital for Lendlease.

Over 52 weeks of construction, 15,665 hours were worked to lay 6,500m2 of metal roof across 17 different roof areas. Roofing was also completed over stairways, walkways and courtyards, with over 1,150 metres of guttering also installed.

The upgrade to Gosford Hospital was completed within the functioning hospital environment as well as the adjoining new construction.

Congratulations to everyone for delivering this project with a safe completion and a special thank you to the project team, subcontractors and suppliers that have helped throughout the project.

  • Gartner Rose Gosford Hospital Redevelopment
  • Gartner Rose Gosford Hospital Redevelopment

Accreditations


Supply Nation Member
HIA
Master Builders Association NSW member

Gartner Rose would like to acknowledge the traditional custodians of this land. We pay our respects to Elders past, present and emerging.
We recognise their culture, traditions and connections to the land.

© 2024 Gartner Rose Pty Ltd. All rights reserved.