St John’s College Stage 3 Project Completion
Gartner Rose is delighted to announce the safe and successful completion of the stage 3 refurbishment works for the commercial kitchen within the beautiful 1868 heritage listed St John’s College at the University of Sydney.
Over 8 weeks of construction, 1,110 hours were worked to complete the refurbishment of the commercial kitchen. With careful planning, the works were undertaken within a live environment with no impact on college operations or the residents living in the college.
The refurbishment works included the installation of a hygienic wall system, further to new covering and waterproofing throughout. In addition, all stainless-steel fixtures were rejuvenated and all equipment was reinstated to its original location.
This project complements our previous work completed on site (stages 1 and 2), as we now move into stage four of the works.
Congratulations to everyone for bringing this project to a safe completion and a special thank you to the project team, subcontractors and suppliers.