Successful WE18 Possession at Mt Colah Station


We are delighted to advise the safe and successful utilisation of the WE18 possession over the weekend of the 29th and 30th of October at Mt Colah Station.

Over the possession weekend, 55 persons worked a total of 660 hours. The station was ready for commuters by Monday morning.

As part of the Possession WE18 at Mt Colah Station, Gartner Rose undertook the following scope:

  • tree & vegetation removal on Pierre Close,
  • platform tree removed,
  • LV power supply elevated out of the platform,
  • installation of temporary ULX,
  • site clearance for new pad mount on Pacific Highway,
  • removal of old Boundary fence,
  • installation of a temporary fence on Pacific Highway,

The possession was finished with zero FAIs, MTIs, or incidents.

Congratulations and thank you to the Gartner Rose staff, Sydney Trains, our subcontractors, and suppliers.

Accreditations


Supply Nation Member
HIA
Master Builders Association NSW member

Gartner Rose would like to acknowledge the traditional custodians of this land. We pay our respects to Elders past, present and emerging.
We recognise their culture, traditions and connections to the land.

© 2024 Gartner Rose Pty Ltd. All rights reserved.