Successful WE37 Possession at Bardwell Park Station
We are delighted to advise the safe and successful utilisation of the WE37 possession at Bardwell Park Station.
As part of the WE37 possession, the following scope was undertaken:
- Relocation and diversion of existing station services, i.e., FLR’s CCTV, Lighting
- Establishment of 400t crane for possession works
- Installation of temporary stair to island platform
- Demolition of the existing stair and foundations
- Construction of platform and bridge level hoardings
- Installation of temporary two ULX’s at City end of platform
Throughout the possession, 91 workers attended site over the two days with a total of 1,624 hours worked. The possession was completed with zero FAIs, MTI’s or incidents.
Congratulations and thank you to the Gartner Rose staff, Sydney Trains, our subcontractors and suppliers.
Michael, Marc and Daniel