Successful WE45 Possession at Bardwell Park Station
We are delighted to advise the safe and successful utilisation of the WE45 possession at Bardwell Park Station.
As part of the WE45 possession, the following scope was undertaken:
- Relocation of station services i.e., FLRs, CCTV and Ticket Vending Machine
- Demolition of platform canopy
- Earthing and Bonding continuity testing
- Survey of existing corridor drainage
- Establishment of a 400t crane
- Completed 7no 750mm diameter piles at varying depths between 11-14m
- Completed 1no 650mm diameter pile at a depth of 12m
Throughout the possession, 121 workers attended site over the two days with a total of 2,257 hours worked.
The possession was completed with zero FAIs, MTIs or incidents.
Congratulations and thank you to the Gartner Rose staff, Transport for NSW, Sydney Trains, our subcontractors and suppliers.