Successful WE18 Possession at Mount Colah Station
We are delighted to advise the safe and successful utilisation of the WE18 possession over the weekend of the 28th and 29th of October at Mount Colah Station.
Over the possession weekend, 38 persons attended site across the two days, working a total of 776 hours.
Gartner Rose undertook the following scope:
- Concrete pours to Platform Stairs and Lift Shaft
- Service trenching on platform: Installation of CSR containment, Stormwater
- Removing materials off platform
- Temporary Electrical works
- Connecting the FAT sewer into the existing platform sewer line
- Placing equipment and materials onto the platform for SSER building
The possession was completed with zero FAIs, MTI’s or incidents.
Congratulations and thank you to the Gartner Rose staff, Sydney Trains, our subcontractors and suppliers.