Gartner Rose All Saints Senior College Casula

All Saints Senior College Casula Project Completion


Gartner Rose is delighted to announce the successful completion of the science labs at Casula for Bovis Lend Lease.

Throughout the project, a total of 9,022 hours were worked during a 45 week period, with zero lost time injuries.

The scope of works involved the new construction of four science labs, one prep room, one chemical storage room, new access road and landscaping.

Works involved screw piling, suspended concrete floor slab, structural steel framework, clad in Scyon Axon vertical FC sheeting together with plasterboard, vinyl and carpet floor linings, wet lab joinery and furniture including fume cupboards, data and Interactive learning equipment in line with CEO vision for interactive learning into the 21st century.

This building was constructed on the side of a steep ravine in unstable ground conditions. Also in a bushfire prone area the building required a level of construction in accordance with strict bushfire controls.

Congratulations to all involved on a safe and successful project.

  • Gartner Rose All Saints Senior College Casula
  • Gartner Rose All Saints Senior College Casula
  • Gartner Rose All Saints Senior College Casula
  • Gartner Rose All Saints Senior College Casula
  • Gartner Rose All Saints Senior College Casula
  • Gartner Rose All Saints Senior College Casula
  • Gartner Rose All Saints Senior College Casula
  • Gartner Rose All Saints Senior College Casula
  • Gartner Rose All Saints Senior College Casula

Accreditations


Supply Nation Member
HIA
Master Builders Association NSW member

Gartner Rose would like to acknowledge the traditional custodians of this land. We pay our respects to Elders past, present and emerging.
We recognise their culture, traditions and connections to the land.

© 2024 Gartner Rose Pty Ltd. All rights reserved.