Gartner Rose Point Clare Station Upgrade

Successful WE18 Possession at Point Clare Station


We are delighted to advise the safe and successful utilisation of the WE18 track possession over the weekend of the 30th and 31st October at Point Clare Station.

Over the possession weekend, 95 persons worked 1030 hours to achieve 100% of the scope for Monday morning. As part of the Possession WE18 at Point Clare Station, Gartner Rose completed a 14m underline crossing (ULX) under both tracks for the route of combined service. 5no of continuous flight auger (CFA) piles up to a depth of 16.5m. Possession prep includes the construction of a 600mm thick piling pad. A shoring system was installed in the ground before pilling to allow excavation of lift pits post-possession.

Congratulations and, thank you to the Gartner Rose staff, Transport for NSW project team, our subcontractors, and suppliers for the effective utilisation of Possession WE18 at Point Clare Station.

Read more on this project here.

Accreditations


Supply Nation Member
HIA
Master Builders Association NSW member

Gartner Rose would like to acknowledge the traditional custodians of this land. We pay our respects to Elders past, present and emerging.
We recognise their culture, traditions and connections to the land.

© 2024 Gartner Rose Pty Ltd. All rights reserved.