Successful WE37 Possession at Mount Colah Station
We are delighted to advise the safe and successful utilisation of the WE37 possession at Mount Colah Station.
As part of the WE37 possession, the following scope was undertaken:
- Installation of 6no 19m long 17ton precast concrete planks
- Installation of 6no 12m long 8ton precast concrete planks
- Installation of 8 prefabricated temporary modular bridge screens
- Excavation of approx. 250m of CSR and hydraulic trenching
- Backfilling of approx. 250t on materials to trenching
- Installation of the platform lift 2 turret, lift lobby screens and canopy
- Construction of 2no pile footings and head stocks for new overhead wiring stanchions
- Removal of 200m of timber hoarding and reinstatement of approx. 100m of temporary fencing
Throughout the possession, 219 workers attended site over the two days with a total of 2,650 hours worked. The possession was completed with zero FAIs, MTI’s or incidents.
Congratulations and thank you to the Gartner Rose staff, Sydney Trains, our subcontractors and suppliers.
Michael, Marc and Daniel.