Gartner Rose Waitara Station Upgrade

Successful WE04 Possession at Waitara Station


Despite the adverse weather, we are delighted to advise the safe and successful utilisation of the WE04 track possession over the weekend of the 23rd and 24th of July at Waitara Station.

Over the possession weekend, 39 persons worked a total of 504 hours. The station was ready for commuters by Monday morning.

As part of the Possession WE04 at Waitara Station, Gartner Rose undertook the following scope:

  • 16 piles demolished,
  • 4 pile caps were tied and poured,
  • 12 linear metres of back blinding was poured,
  • 2 temporary decks reinstated,
  • minor excavation around the platform walls to help future works.

The possession was finished with zero FAIs, MTI’s or incidents.

Congratulations and thank you to the Gartner Rose staff, Transport for NSW project team, our subcontractors, and suppliers.

Accreditations


Supply Nation Member
HIA
Master Builders Association NSW member

Gartner Rose would like to acknowledge the traditional custodians of this land. We pay our respects to Elders past, present and emerging.
We recognise their culture, traditions and connections to the land.

© 2024 Gartner Rose Pty Ltd. All rights reserved.