Kogarah Station Lift Replacement


During 16 weeks of construction, including multiple possessions, 4,528 hours were worked to complete the replacement of two lifts at Kogarah Station.

The project scope included dismantling and removing two existing lifts followed by the installation of two new fifteen passenger lifts. Modification works to the existing lift shafts were undertaken to comply with new standards and accommodate the replacement lift cars, including waterproofing, structural alterations and painting of surrounding surfaces. Internal and external cladding works, further to new louvres, were also undertaken to the lift shafts.

Associated services were upgraded with new mechanical installations, as well as a full electrical install including lighting and CCTV in addition to wet and dry fire upgrades involving new smoke detectors and sprinklers.

All works were completed four days ahead of programme.

Sector

Rail

Value

$850k

Client

Sydney Trains

Duration

July 2020 - October 2020

  • Kogarah Station Lift Replacement
  • Kogarah Station Lift Replacement

Related Projects


Accreditations


Supply Nation Member
HIA
Master Builders Association NSW member

Gartner Rose would like to acknowledge the traditional custodians of this land. We pay our respects to Elders past, present and emerging.
We recognise their culture, traditions and connections to the land.

© 2024 Gartner Rose Pty Ltd. All rights reserved.