Kogarah Station Lift Replacement
During 16 weeks of construction, including multiple possessions, 4,528 hours were worked to complete the replacement of two lifts at Kogarah Station.
The project scope included dismantling and removing two existing lifts followed by the installation of two new fifteen passenger lifts. Modification works to the existing lift shafts were undertaken to comply with new standards and accommodate the replacement lift cars, including waterproofing, structural alterations and painting of surrounding surfaces. Internal and external cladding works, further to new louvres, were also undertaken to the lift shafts.
Associated services were upgraded with new mechanical installations, as well as a full electrical install including lighting and CCTV in addition to wet and dry fire upgrades involving new smoke detectors and sprinklers.
All works were completed four days ahead of programme.
Sector
Rail
Value
$935k
Client
Sydney Trains
Duration
July 2020 - October 2020