Gartner Rose Mount Colah WE50 Possession

Successful WE50 Possession at Mt Colah Station


We are delighted to advise the safe and successful utilisation of the WE50 possession over the weekend of the 10th, 11th and 12th of June at Mt Colah Station.

Over the possession weekend, 106 persons worked a total of 2,066 hours, with the station made ready for commuters by Tuesday morning.

As part of the WE50 possession at Mt Colah Station, Gartner Rose undertook the following scope:

  • Establishment of traffic control measures on Pacific Highway and Pierre Close
  • Completion of platform excavation works, placement of footing reo and pouring of concrete
  • Construction of platform support columns for the new bridge and stair infrastructure
  • Construction of 140m of platform hoardings
  • Installation of temporary CCTV onto platform hoardings
  • Installation of permanent VAM units
  • Completion of piling works on Pacific Highway – 12no piles

The possession was finished with zero FAIs, MTI’s or incidents.

Congratulations and thank you to the Gartner Rose staff, Sydney Trains, our subcontractors and suppliers.

  • Gartner Rose Mount Colah WE50 Possession
  • Gartner Rose Mount Colah WE50 Possession
  • Gartner Rose Mount Colah WE50 Possession
  • Gartner Rose Mount Colah WE50 Possession
  • Gartner Rose Mount Colah WE50 Possession
  • Gartner Rose Mount Colah WE50 Possession

Accreditations


Supply Nation Member
HIA
Master Builders Association NSW member

Gartner Rose would like to acknowledge the traditional custodians of this land. We pay our respects to Elders past, present and emerging.
We recognise their culture, traditions and connections to the land.

© 2024 Gartner Rose Pty Ltd. All rights reserved.