Gartner Rose Waitara WK51 Site Possession

Successful WK51 Mid-Week Possession at Waitara Station


We are delighted to advise the safe and successful utilisation of the WK51 mid-week possession on the 19th – 22nd of June at Waitara Station.

Throughout the possession, 15 persons worked a total of 236 hours over two nights. All works were completed with the use of a 150T crane working with the power out and under level 5 conditions.

As part of the WK51 mid-week possession at Waitara Station, Gartner Rose undertook the following scope:

  • Installation of carpark (western) canopy
  • Removal of 3t excavator from platform
  • Construction and waste material lifts to and from the island platform.

The possession was completed with zero FAIs, MTI’s or incidents.

Congratulations and thank you to the Gartner Rose staff, Transport for NSW, our subcontractors and suppliers.

  • Gartner Rose Waitara WK51 Site Possession
  • Gartner Rose Waitara WK51 Site Possession
  • Gartner Rose Waitara WK51 Site Possession

Accreditations


Supply Nation Member
HIA
Master Builders Association NSW member

Gartner Rose would like to acknowledge the traditional custodians of this land. We pay our respects to Elders past, present and emerging.
We recognise their culture, traditions and connections to the land.

© 2024 Gartner Rose Pty Ltd. All rights reserved.