Successful WE50 Possession at Beecroft Station Upgrade


We are delighted to advise the safe and successful utilisation of the WE50 track possession over the long weekend of the 12th, 13th and 14th of June at Beecroft Station.

Over the possession weekend, 244 persons worked a total of 2493 hours to complete 100% of the work required and the station was ready for commuters by Tuesday morning.

As part of the Possession WE50 at Beecroft Station, Gartner Rose undertook:

  • Complete installation of platform canopy
    • Platform canopy size: 450m²
    • Platform canopy steel: 14 tonnes
    • 60t crane supporting a 150t crane with fly-jib
  • Regrade and resurface of country end of platform including footing for station furniture
  • Complete drainage ULX
  • Complete brickwork to Lantern Building
  • Partial cut-over of power supply
  • Cutover of communication services

The possession was finished with zero FAI’s, MTI’s, LTI’s or incidents.

Accreditations


Supply Nation Member
HIA
Master Builders Association NSW member

Gartner Rose would like to acknowledge the traditional custodians of this land. We pay our respects to Elders past, present and emerging.
We recognise their culture, traditions and connections to the land.

© 2024 Gartner Rose Pty Ltd. All rights reserved.