Successful WE50 Possession at Niagara Park Station
We are delighted to advise the safe and successful utilisation of the WE50 track possession over the long weekend of the 12th, 13th, and 14th of June at Niagara Park Station.
Over the possession weekend, 114 persons worked a total of 943 hours to complete 100% of the work required and the station was ready for commuters by Tuesday morning.
As part of the Possession WE50 at Niagara Park Station, Gartner Rose undertook:
- Install platform lift shaft lower canopy and upper screens.
- Install lift 3 screens.
- Regrade/ Resurface both car parks and platform. 175T of asphalt in total.
- Commission new station power supply upgrade and station service mains switchboard.
- Caulking of lift shafts.
- Hoarding removal/furniture reinstatement.
The possession was finished with zero FAI’s, MTI’s, LTI’s or incidents.