Gartner Rose Lilyfield Light Rail Yard

Lilyfield Light Rail Yard


During 38 weeks of construction, over 4,500 hours were worked to complete the roofing of the Maintenance Building, Fire Pump Building and the Substation Building at the Lilyfield Light Rail Yard.

3,300m2 of Kingspan insulated roof sheeting was installed to the Maintenance Building, as well as 250m2 of thermally insulated skylights and over 500m of Kingspan insulated gutters. The exterior of the building was clad with Fielders boulevard and Longline 305. Cladding was complimented with 6mm thick stainless-steel angles, used to create striking vertical corner caps to the ends of the Maintenance Building.

The Substation and Fire Pump Buildings underwent the installation of 300m2 of Kingspan insulated roof sheeting and the walls were completed with Colorbond Matte Boulevard cladding.

Sector

Civil and Commercial, Roofing

Value

$1.2 million

Client

Coleman Rail

Duration

July 2018 - April 2019

  • Gartner Rose Lilyfield Light Rail Yard
  • Gartner Rose Lilyfield Light Rail Yard
  • Gartner Rose Lilyfield Light Rail Yard
  • Gartner Rose Lilyfield Light Rail Yard
  • Gartner Rose Lilyfield Light Rail Yard
  • Gartner Rose Lilyfield Light Rail Yard
  • Gartner Rose Lilyfield Light Rail Yard

Related Projects


Accreditations


Supply Nation Member
HIA
Master Builders Association NSW member

Gartner Rose would like to acknowledge the traditional custodians of this land. We pay our respects to Elders past, present and emerging.
We recognise their culture, traditions and connections to the land.

© 2024 Gartner Rose Pty Ltd. All rights reserved.