Pyrmont Pedestrian Crossing
A total of 190 hours were worked to deliver the new pedestrian crossing at the Pyrmont Light Rail Station.
The scope involved the removal and disposal of all 12 existing timber crossing panels, the installation of new precast concrete panels and associated foundations to complete the new pedestrian crossings. The scope was finished with painted pedestrian crossing markings, with the majority of the works taking place during a possession weekend.
Sector
Rail
Value
$165k
Client
Transdev
Duration
September 2018 - October 2018