SUCCESSFUL POSSESSION - Point Clare 12 & 13th March (WE37)

Main Image

Over the possession weekend, 75 persons worked a total of 836 hours to complete the work required and the station was ready for commuters by Monday morning. Balance of works were completed under the preapproved Level 5 permit during the following days.

Further work achieved over the possession weekend included:

  • 2x 5m bored piles with temporary casing below live 11kV power lines
  • 2x 6m bored piles with temporary casing
  • 2 major inground steel obstructions removed from piles at a depth of up to 3m
  • Temporary toilet installed to Brisbane waters drive car park